In a significant decision, the High Court has found construction giant J Hutchinson and the CFMEU were not complicit in anticompetitive behaviour despite the builder terminating a non-union contractor under threat of industrial action.
The case highlighted how autonomously capitulating to a demand – without communicating any commitment to do so with the threatening party – fails to establish an illegal arrangement or understanding.
Ending a three-part legal process, the Australian Competition and Consumer Commission (ACCC) on April 2 lost its appeal against an earlier Full Federal Court decision siding with Hutchinson and the CFMEU.
The Full Court appeal overturned an initial Federal Court determination in favour of the ACCC’s allegations.

In the Full Court, the ACCC unsuccessfully asserted that Hutchinson had shown, through succumbing to threats from the CFMEU of industrial action if a non-union subcontractor was allowed back on site – by ultimately terminating the contract – that it had reached a “consensus” with the union and “communicated its assent in that regard”.
During its High Court appeal, the competition watchdog contended an “inference” was sufficient to establish Hutchinson arrived at an arrangement or understanding with the CFMEU.
However, the High Court ultimately rejected the argument.
Background
Hutchinson was the head contractor on Brisbane’s Southpoint A Apartments project.
In March 2016, the builder entered into a subcontract for waterproofing works at the site.
An enterprise bargaining agreement between Hutchinson and the CFMEU obliged Hutchinson to consult with the CFMEU about the appointment of subcontractors in certain circumstances, and the CFMEU had previously urged Hutchinson to retain subcontractors with enterprise bargaining agreements.
The waterproofing subcontractor did not have an enterprise bargaining agreement with the CFMEU.
It performed work at the project site in April and May 2016.
On 11 June 2016, a CFMEU representative told Hutchinson’s project manager that the CFMEU would “sit the job down” if the subcontractor was allowed back on site.
Hutchinson reacted to the CFMEU’s threat of industrial action by excluding the subcontractor from the site and terminating the subcontract on 26 July 2016.
The High Court’s Chief Justice Gageler, Justice Gleeson and Justice Beech-Jones explained:
“The appellant, the ACCC, contends that, contrary to the reasoning of the Full Court (of the Federal Court), it was sufficient to give rise to an understanding for the purposes of s 45E(3) [of the Competition and Consumer Act] that Hutchinson succumbed to the CFMEU’s threat of industrial action, responding by doing what was demanded under sanction of that threat.
“… The contention of the ACCC must be rejected. A person who succumbs to a threat of industrial action by doing what is demanded under sanction of the threat, without express or tacit communication of a commitment to do so, does not arrive at an understanding with the person who makes the threat for the purposes of s 45E(3) (and s 45EA) of the Act.
“It follows that the appeals must be dismissed.”
Primary judge – anti-competitive behaviour and penalties over $1.3 million
The Full Federal Court (Wigney, Bromwich and Anderson) had previously unanimously allowed appeals of orders made by the primary judge who found that Hutchinson had contravened the CC Act by “making an arrangement or arriving at an understanding” with the CFMEU.
Justice Downes imposed penalties of $600,000 on Hutchinson and $750,000 on the CFMEU for its conduct in being knowingly concerned in, or party to, and inducing Hutchinson’s contraventions.
But the Full Court determined the judge’s findings of “manifestations of mutual consent to carry out a common purpose” did not “take what occurred beyond Hutchinson merely succumbing to threats by the CFMEU”.
It followed, according to the Full Court, that the primary judge’s “finding of the existence of the alleged arrangement or understanding could not stand”.
ACCC tries to ‘snatch victory from the jaws of defeat’
The High Court indicated the ACCC’s appeal was on shaky ground, calling it “an attempt to snatch victory from the jaws of its defeat”.
Chief Justice Gageler, Justice Gleeson and Justice Beech-Jones:
“No longer contending that Hutchinson made an arrangement with the CFMEU, the ACCC contends that the inference is sufficient to establish that Hutchinson arrived at an understanding with the CFMEU. The ACCC founds that contention on the proposition that ‘if one person makes a threat and demand to a second person, and the second person capitulates to that threat and acts as demanded, what has arisen is an understanding for the purposes of the Act’”.
The judges added: “The proposition is too broad.”

Instead, the High Court considered the words “contract, arrangement or understanding”, and found the relevant part of the CC Act referred to “a spectrum of consensual dealings”… in which the words “arrangement” and “understanding” each described something less than a legally binding contract.
The CC Act distinguished between contracts and arrangements, which were “made”, and understandings, which are “arrived at”.
“The act of a person succumbing to a threat does not, without more, amount to arrival at an understanding to do what is demanded. The act may be explicable as a rational, commercial response to the threat rather than a form of collusive behaviour aimed at achieving a proscribed purpose”.
A fourth High Court judge, Justice Edelman, noted separately that a contract, arrangement or understanding requires reciprocal conduct between two or more people:
“The result of this case might have been different if (the CC Act) had proscribed unilateral conduct arising from an “undertaking”, “demand” or “threat”, all of which can arise without any proof of reciprocity. But (its) history, text, and context make clear that an arrangement or understanding, like a contract or a combination or conspiracy, requires reciprocity. Without communication of assent to the party making an offer, request or demand, no contract, arrangement or understanding can be formed with the other party unless the party making the offer, request or demand expressly or impliedly dispenses with the need for such communication.”
Implications for employers
This matter does not depart from long-established case law requiring communication of assent between parties to establish an arrangement or understanding.
Where a party (in this case the ACCC) wishes to demonstrate a boycott or collusion, it must be able to show one party agreed to do whatever the other party was pressuring it to do. Mere cause and effect will not meet the evidentiary burden of “reciprocity of conduct”.
The High Court did indicate the requirement for assent can be dispensed with – if evidence revealed there was no need to communicate the assent to the agreed conduct.
In fact, Justice Edelman said the outcome could have been different had the ACCC established that the union dispensed with the need to communicate the assent of Hutchinson to the CFMEU’s threat “so that an arrangement or understanding would have been formed by Hutchinson terminating (the subcontractor) in a manner objectively referable to the demand by the CFMEU.
“But the ACCC did not run such a case and made no submissions to that effect.”
Interestingly, the High Court did note a “mild assurance” of agreement may be enough to establish an arrangement or understanding. No doubt this phrase will be the subject of future litigation.